How Long Does Concrete Take to Cure?

Keep new concrete moist and above 50°F for at least 3 to 7 days (NRMCA); Quikrete says 5 days in warm weather and 7 in cooler weather. Concrete is specified at its 28-day strength, and a standard bag mix reaches about 63% of it at 7 days.

Updated How we price

On this page
  1. Setting, curing and drying
  2. How long to cure
  3. Strength by day
  4. Curing methods
  5. Cold and hot weather
  6. Related
  7. FAQ
  8. Sources

Setting, curing and drying

Three different things happen to new concrete:

  • Setting: the mix stiffens and can no longer be worked. A fast-setting bag mix reaches final set in 20 to 40 minutes [7].
  • Curing: keeping the concrete “at adequate moisture and temperature conditions so that it can develop properties, such as strength and durability” [1].
  • Drying: water evaporating. Concrete Network puts it plainly: curing is the chemical process that gives concrete strength, drying is just moisture leaving [3].

How long to cure

SourceCuring period
NRMCA [1]At least 3 to 7 days, or as the specification requires
Quikrete, standard mix 1101 [2]5 days at 70°F or warmer; 7 days at 50 to 70°F
Concrete Network [3]Keeping the surface wet for 7 days “is still the best way”

Curing matters: NRMCA says concrete that dries out early can lose as much as 50% of its potential strength compared with moist-cured concrete [1].

Strength by day

Concrete strength is normally specified at 28 days [4]. Quikrete’s data sheets give these compressive strengths:

Mix2 hours24 hours7 days28 days
Standard Concrete Mix 1101 [2]——2,500 psi4,000 psi
Fast-Setting Mix 1004 [7]400 psi1,000 psi2,500 psi4,000 psi

For the standard mix, 2,500 of 4,000 psi means about 63% of its 28-day strength at 7 days (our calculation from the data sheet).

Curing methods

  • Keep it wet. Continuous fogging or sprinkling works well; alternate wetting and drying does not [1].
  • Cover it. Plastic sheets at least 4 mils thick hold the moisture in [1].
  • Curing compound. Sprayed on as soon as the water sheen has gone from the surface [1]. A cure-and-seal product such as Quikrete 8730 typically goes on 4 to 6 hours after placing [8].

Cold and hot weather

  • Keep it above 50°F while it cures [1].
  • Cold weather is when, for more than 3 days in a row, the average daily temperature is below 40°F and the air stays at or below 50°F for more than half of each day. A 20°F drop in concrete temperature roughly doubles the setting time [5].
  • Freezing. Fresh concrete freezes below about 25°F. Protect it until it reaches 500 psi, about two days after placement [5]. Quikrete: protect from freezing for the first 48 hours [2].
  • Hot weather. Concrete cured hot “will not be as strong at later ages” as concrete cured near 70°F. NRMCA says to keep curing for at least 3 days [6].

When you can walk or park on it: walking and driving on new concrete. Planning the pour: slab calculator, bags of concrete calculator.

Frequently asked questions

How long does concrete take to cure?

NRMCA says curing should continue for at least 3 to 7 days, or as long as the specification requires. Quikrete's instructions for its standard mix are 5 days at 70°F or warmer and 7 days at 50 to 70°F. Concrete keeps gaining strength after that; it is specified at 28 days.

What is the difference between curing and drying?

Concrete Network: drying is water evaporating, while curing is the chemical process that gives concrete its strength. Concrete that dries out too early stops curing.

Does concrete get weaker if it isn't cured?

Yes. NRMCA says concrete left to dry out can lose as much as 50% of its potential strength compared with concrete that was kept moist.

Can you pour concrete in cold weather?

Yes, with protection. NRMCA says fresh concrete freezes below about 25°F and must be protected until it reaches 500 psi, about two days after placement. Quikrete says to protect its mix from freezing for the first 48 hours.

Should I water new concrete?

Keeping it continuously wet is one of the best curing methods: NRMCA lists fogging or sprinkling, and Concrete Network says keeping the surface wet for 7 days is still the best way. NRMCA warns that alternate wetting and drying is not acceptable.

Sources

  1. NRMCA, CIP 11: Curing in-place concrete, updated 2017. Checked September 23, 2026.
  2. Quikrete, Concrete Mix No. 1101 data sheet, updated 2022-10. Checked September 23, 2026.
  3. Concrete Network, Concrete curing guide, updated 2025-05-06. Checked September 23, 2026.
  4. NRMCA, CIP 35: Testing compressive strength of concrete. Checked September 23, 2026.
  5. NRMCA, CIP 27: Cold weather concreting. Checked September 23, 2026.
  6. NRMCA, CIP 12: Hot weather concreting, updated 2014. Checked September 23, 2026.
  7. Quikrete, Fast-Setting Concrete Mix 1004-60 data sheet. Checked September 23, 2026.
  8. Quikrete, Acrylic Concrete Cure & Seal 8730 data sheet. Checked September 23, 2026.